Cement Board Ceramic Tile

The best base for ceramic tile is waterproof cement board.

Installing cement board correctly is the most critical part of a first-class tiling project. Here's how to do it.

By the DIY experts of The Family Handyman Magazine

TIME

One day

COMPLEXITY

Simple

COST

$20 - $100

Step 1: Overview

The traditional method of installing ceramic tile called for setting it in a solid mortar bed. Troweling a perfectly flat bed required great skill, but the reward was a tile job that lasted for decades. Today, most professional tile setters back their tile with cement board instead, because it offers almost the same durability with a lot less work. And the best part? Do-it-yourselfers can use it too.

Cement board is a thin layer of mortar sandwiched between sheets of fiberglass mesh cloth. The 1/2-in. thick board is unaffected by water, making it a great substitute for a mortar bed.

In this article, we'll show you how to create a strong, durable and waterproof tile base around your bathtub using cement board. We chose the tub surround because it's highly leak-prone, and an ideal spot for cement backer board. Although cement board is heavy and a bit awkward to cut, even a novice should be able to complete a professional-quality tub surround, ready to tile, in a day. (Allow half a day to tear out the old tile and perhaps several more days to let damp wood dry out.)

Figure A: Cement Board Installation Details

Add blocking and other framing details before hanging the cement board.

Fig. A Installation details Figure A: Installation details
Fig. B Figure B: Coated cement board screw
Back to Top

Step 2: Buying materials

Cement board, technically called cementitious backer unit (CBU), is manufactured under different brand names. The standard size sheet is 3 x 5 ft. and 1/2 in. thick, weighs 45 to 60 lbs. and is available at most full-service lumberyards and building supply centers. The 1/2-in. thick cement board spans studs spaced 16 in. on center. Other sizes, like 3 x 4 ft., 3 x 6 ft. and 4 x 4 ft., are available, but you may have to contact a tile supplier to find them. Our project, tiling the walls around a standard 5-ft. tub to a height of 6 ft., requires four 3 x 5-ft. sheets.

To attach the cement board to the studs, you'll need special 1-1/4 in. cement board screws (see Fig. B). These screws have a coating to resist corrosion, a special wide head with cutting flutes and hi-low threads for a strong grip. If you can't find them at a home center, call tile specialty stores. If special screws aren't available, attach the cement board with 1-1/2 in. hot-dipped galvanized roofing nails.

You'll also need a roll of 2-in. wide fiberglass mesh cement board tape and a 25-lb. bag of thin-set adhesive, both available at home centers. The thin-set is a cement-based powder that you mix with water or latex additive to form a thick paste, which is used to seal the seams in the board and can also be used to set the tile.

Finally, you'll need an 8 x 12-ft. piece of 4-mil plastic sheeting and some straight 2x4s.

Back to Top

Step 3: Getting started

Protect the bathtub with a dropcloth and seal the edges with tape to keep out debris. Tear out the old tile and backing to the bare studs. You'll have to remove the faucet handles, tub spout and shower head.

Now's the time to straighten crooked studs and add blocking (Photos 1 and 2). This is a critical step. Tile is easier to set and looks better on a straight wall. Extra blocking installed now makes it easier to screw in the edges of the cement board later.

Measure the thickness of the drywall or plaster where the cement board will meet it. If this dimension is more than 1/2 in., add strips of wood to the studs so the cement board will be precisely flush with the old wall.

While your walls are open:

  • Add wood blocking now where you will be installing towel bars, grab bars or shower doors; then you won't have to rely on those frustrating little plastic anchors to hold up your fixtures.
  • Upgrade the insulation on outside walls with new, higher R-value fiberglass batts.
  • You can replace your old tub faucet with a new pressure-balancing shower valve.

Back to Top

Step 4: Waterproof the walls

Staple 4-mil plastic to the studs (Photo 3). Use a single piece to avoid seams. Push the plastic tightly into the corners before stapling to avoid creating a bridge of plastic that will tear when you install the cement board. The plastic serves as a vapor barrier for the insulated wall and as a last defense against any water that may sneak through the tile and cement board.

Back to Top

Step 5: Hang the cement board

When the prep work is done, start the rewarding job of hanging the cement board. All your hard work will start to pay off as the first sheet goes up.

Photos 4 through 9 show how to measure, cut and drill cement board. Wear a NIOSH-approved dust mask and eye protection when cutting or drilling cement board.

Hanging cement board is one job where gaps are desirable. Space the bottom sheets 1/4 in. above the tub lip to allow for movement of the tub and floor. Use nails or screws as temporary spacers to create a 1/8-in. gap between sheets of cement board. When you squeeze the thin-set mortar into this gap, it will lock the two sheets together and strengthen the seam. Finally, leave extra clearance around each piece by deducting about 1/4 in. from your measurements before you mark the cement board for cutting. Believe me, you want to avoid the knuckle-skinning task of trimming a little off. Any gaps will be covered with mesh tape and thin-set.

You'll ruin a couple of knife blades while cutting (Photo 5), so keep some extras handy. Use carbide grit jigsaw blades to cut cement board. You can also use regular blades, though they'll wear out after a few cuts.

Cement board has a smooth side and a rough side. Face the rough side out if you will be using thin-set mortar adhesive to install the tile but the smooth side out if you will be using latex mastic.

Back to Top

Step 6: Finishing up

Complete the job by piecing in any missing drywall and taping the seams (Photo 11). Cover all of the corners and seams, including the joint where drywall and cement board meet, with the fiberglass mesh tape.

Following the manufacturer's recommendations, mix the thin-set mortar adhesive with enough water to form a thick paste. Wear a NIOSH-approved dust mask when mixing the powder. Spread the thin-set over the tape (Photo 12).

When you're done covering the tape with thin-set, you're ready to tile. You don't even have to let the thin-set dry. Don't worry if the tile doesn't cover the joint between the cement board and the drywall. Just finish it with a setting-type joint compound, which comes in 25-lb. bags of powder that you mix with water. (It's available at home centers.) Setting-type compound is stronger and more water-resistant than the type that hardens by drying.

Back to Top

Required Tools for this Project

Have the necessary tools for this DIY project lined up before you start—you’ll save time and frustration.

  • Cordless drill
  • Jigsaw
  • Stapler
  • Straightedge
  • Utility knife
  • Taping knife

Required Materials for this Project

Avoid last-minute shopping trips by having all your materials ready ahead of time. Here's a list.

  • Cement board
  • Thin-set mortar
  • Cement board screws
  • 2 x 4s
  • Fiberglass mesh tape (use the special, heavier type sold for use with thin-set mortar — drywall mesh tape will rot)